User:Doug/Kitchen renovation: Difference between revisions
initial draft |
add unisexurinal link |
||
| (4 intermediate revisions by the same user not shown) | |||
| Line 1: | Line 1: | ||
This page is to plan for the future kitchen. | |||
== | == Aim == | ||
To create a kitchen that will: | To create a kitchen that will: | ||
| Line 9: | Line 9: | ||
* allow for a higher level of hygiene | * allow for a higher level of hygiene | ||
== | == Location == | ||
* | * Current: K20-1-2 | ||
** | * Proposed: K20-1-1 (currently Snack kitchen) + K20-1-1B (currently Snack kitchen "Kabuff") | ||
** 👍 has water and waste water connections | |||
** 👍 not a pass-through room | |||
** 👍 quite central | |||
** 👍 would be next to the proposed future snack kitchen | |||
** 👎 on the smaller side | |||
*** but no passage space! | |||
(The plan to swap Kitchen and Snack kitchen locations is already kind of underway: the recent (late 2025) window exchange put a window-door in the K20-1-2, with the aim to eventually put a balcony there.) | |||
== | == Plan == | ||
=== Preparation === | |||
Currently some plumbing runs through the room which is in active use in the [[Main bathroom]] and lower staircase toilet. | |||
* ☐ move toilet in main bathroom K20-2-1 to "Kabuff" K20-2-1B (See Appendix) ❓ | |||
** ☐ 🧩 acquire "good" toilet (i.e. one that doesn't block, preferably with urine separation) or all-bodies-urinal (e.g. [https://finizio.de/shop/unisexurinal/ from Finizio]) | |||
** ☐ free up the left side of Kabuff | |||
** ☐ drill necessary holes to upper-staircase toilet (~50 cm) | |||
** ☐ water off! | |||
** ☐ install toilet, cistern, bidet hose & connect everything up (!) | |||
** ☐ reinstall the old door or a curtain | |||
** ☐ remove old toilet, cap off the tube | |||
* ☐ supply water to lower staircase toilet from upper staircase toilet (or wash kitchen) | |||
** ☐ drill hole | |||
** ☐ water off! | |||
** ☐ switch connections | |||
=== Temporary Snack kitchen | === Temporary Snack kitchen ❓ === | ||
K20-1-1 will be unusable for the duration of works. It is possible the work will be done in a month, but maybe longer, so the "temporary" rearrangement should be good for at least 2 months. Options: | |||
* | * if weather allows, set up a a temporary outdoor "main" kitchen and set up new Snack kitchen "permanently" in current Kitchen (i.e. k20-1-2) | ||
** more work to begin, less at end, food preparation more distributed | ** more work to begin, less at end, food preparation more distributed | ||
* set up temporary Snack kitchen in Elephant room | * set up temporary Snack kitchen in Elephant room | ||
| Line 53: | Line 50: | ||
This phase of the work is about getting rid of unwanted things and getting the room to a stage where positive construction can begin. | This phase of the work is about getting rid of unwanted things and getting the room to a stage where positive construction can begin. | ||
* remove | * ☐ remove mobile items (microwave, glasses, oats, etc) | ||
* ☐ water off! | |||
* | * ☐ remove mounted items (cupboards, shelf, radiator, sink, tap, etc) | ||
* | * ☐ power off! | ||
* | * ☐ remove fake-wall (left side, behind sink) | ||
* remove fake-wall | ** ℹ️ unknown tasks may hide behind wall! | ||
** unknown tasks may hide behind wall! | * ☐ remove unnecessary plumbing | ||
* remove | ** ☐ remove sewage pipe in back-right corner | ||
* | ** ☐ remove water pipes leading to right side | ||
* remove | * ☐ strip walls & ceiling | ||
* remove all | ** ☐ remove all tiles | ||
* remove all wallpaper (including ceiling) | ** ☐ remove all wallpaper (including ceiling) | ||
** needs to be done thoroughly, no pieces of paper left (likely requires spiky roller/water spray) | *** ℹ️ needs to be done ''thoroughly'', no pieces of paper left (likely requires spiky roller/water spray) | ||
* remove | ** ☐ remove all hooks, plugs, clips, etc. | ||
** ☐ break out any loose plaster | |||
** ☐ sand walls, if necessary | |||
** | * celebrate 🎉 | ||
** | |||
* celebrate | |||
=== Building up === | === Building up === | ||
This phase of the work is about positively constructing towards the desired end state. '''A lot of open questions still!''' | This phase of the work is about positively constructing towards the desired end state. '''A lot of open questions still!''' | ||
* if | * ☐ prepare walls & ceiling (i.e. smooth, flat, stable) | ||
* electrics | ** ☐ plaster any holes | ||
** aim | ** ☐ if necessary plastering or complete dry-walling (hopefully not! 🙏) | ||
** | * ☐ electrics | ||
** parapet trunking (power strip) along both sides | ** aim: no exposed wires, good number of sockets where useful | ||
* plumbing | ** ☐ main light switch | ||
** | ** ☐ ovens/stoves ❓ | ||
** | ** ☐ lights ❓ | ||
** do we keep the | ** ☐ parapet trunking (power strip) along both sides ❓ | ||
* | * ☐ plumbing | ||
** | ** ☐ radiator or wall heating ❓ | ||
** | ** ☐ reroute that pipe that sticks out on the "left" side | ||
* | ** ☐ prepare sink inlets & outlet ❓ | ||
* | *** preference: [https://img1.homary.com/mall/file/2021/10/29/26e43c4043c34e81aa7b31c84b70c12a.jpg wall-mounted hose-tap] | ||
* | *** ℹ️ outlet location has a degree of flexibility, wall-mounted tap not | ||
* ... | * ☐ windowsill | ||
* | ** A nice bit or marble? | ||
* ☐ ventilation❓ | |||
* ☐ Kabuff wall ❓ | |||
** if removing (See Appendix), shelves to go all the way | |||
** ℹ️ [https://hardwareheaven.ie/wp/wp-content/uploads/2023/11/sb108-2.jpg "London" style shelf brackets] have a low profile. | |||
* ☐ dry-walling left side | |||
** aim: to be able to have one, long stainless steel work surface without any corners, gaps or cut-outs | |||
**from floor to head-height? | |||
* ☐ ceiling and upper walls | |||
** white paint that can deal with humidity ❓ | |||
* ☐ lower walls | |||
** random saved tiles, 20 cm * 20 cm ❓ | |||
* ☐ flooring | |||
** [https://m.media-amazon.com/images/I/71Jidl6CMFL.jpg coin stud rubber matting] ❓ | |||
* portal through the wall to the snack-kitchen ❓ | |||
* ... unknown unknowns 👻💀👹 ... | |||
* Celebrate! 🎉🎉 | |||
=== Installation === | |||
Note that the specifics of most of these items need to be decided on ''before'' commencing the work at all | |||
* ☐ sink | |||
* ☐ tap | |||
* ☐ tables | |||
** consider differing height requirements | |||
* ☐ overhead storage | |||
* ☐ fridge ❓ | |||
* CelEbRat3!!! 🎉🎉🎉🎉 | |||
== Appendix == | |||
=== Advice === | |||
Who do we know who did a comparable kitchen renovation? How much did it cost, time did it take? Advice? | |||
* ✅ Lebenstraum Gemeinschaft Janishausen - Doug contacted | |||
** 2026-04-21 still no response | |||
=== Sewage pipe === | |||
Remove it or keep it? Removing it permanently gains a little space for the kitchen, simplifies the room shape and infrastructural complexity. Removing also requires work... Options in my order of preference | |||
* remove pipe, relocate bathroom toilet to Kabuff | |||
** significant work | |||
* keep pipe, box it off (drywall) | |||
** moderate work | |||
** long-term missed opportunity | |||
* remove pipe, remove bathroom toilet with no replacement | |||
** the toilet seems useful and used! | |||
* keep pipe, no boxing | |||
** least work | |||
** looks ugly, traps dirt | |||
** (I would not be motivated to help with renovation if this option were chosen) | |||
* remove pipe, reroute sewage through wall to staircase toilets | |||
** most work | |||
** this would require over 2 meters of horizontal sewage routing and a major reorganizing of pipes in upper staircase toilet | |||
** (I would not be motivated to help with renovation if this option were chosen) | |||
=== '''Kabuff separation wall''' === | |||
Remove part/all of it? | |||
* options: | |||
** removing the "small" side towards the entrance would allow a/the shelf to extend all the way to the door, making better use of the space | |||
** as above, but extending all the way up: would allow a/the shelf to extend vertically to roof | |||
** all: unclear... my imagination overflows | |||
* any removal would brings ''significant'' costs and would only make sense to do during main action | |||
** would require architectural considerations, possibly building in supports | |||
** dusty breakage | |||
** significant plastering required | |||
** permanent damage to original and pretty door-frame | |||
** makes it necessary to make all shelving new | |||
* To-do: drill into wall above door frame post: if it extends to the ceiling, it's probably supporting | |||
=== Heating (or not) === | |||
Options and their drawbacks | |||
* Keep radiator (status quo) | |||
** takes space from room | |||
** makes windowsill less accessible | |||
** traps dirt | |||
** increases wall complexity for tiling, etc | |||
* Remove radiator, no replacement | |||
** possibly too cold in winter | |||
*** but likely fine given physical activity + heating from cooking | |||
* Remove radiator, install wall-heating panel | |||
** work: finding parts, mounting, plumbing and plastering | |||
Latest revision as of 16:33, 21 April 2026
This page is to plan for the future kitchen.
Aim
To create a kitchen that will:
- enable preparing food for bigger numbers of people
- be more enjoyable to use
- be easier to clean and maintain
- allow for a higher level of hygiene
Location
- Current: K20-1-2
- Proposed: K20-1-1 (currently Snack kitchen) + K20-1-1B (currently Snack kitchen "Kabuff")
- 👍 has water and waste water connections
- 👍 not a pass-through room
- 👍 quite central
- 👍 would be next to the proposed future snack kitchen
- 👎 on the smaller side
- but no passage space!
(The plan to swap Kitchen and Snack kitchen locations is already kind of underway: the recent (late 2025) window exchange put a window-door in the K20-1-2, with the aim to eventually put a balcony there.)
Plan
Preparation
Currently some plumbing runs through the room which is in active use in the Main bathroom and lower staircase toilet.
- ☐ move toilet in main bathroom K20-2-1 to "Kabuff" K20-2-1B (See Appendix) ❓
- ☐ 🧩 acquire "good" toilet (i.e. one that doesn't block, preferably with urine separation) or all-bodies-urinal (e.g. from Finizio)
- ☐ free up the left side of Kabuff
- ☐ drill necessary holes to upper-staircase toilet (~50 cm)
- ☐ water off!
- ☐ install toilet, cistern, bidet hose & connect everything up (!)
- ☐ reinstall the old door or a curtain
- ☐ remove old toilet, cap off the tube
- ☐ supply water to lower staircase toilet from upper staircase toilet (or wash kitchen)
- ☐ drill hole
- ☐ water off!
- ☐ switch connections
Temporary Snack kitchen ❓
K20-1-1 will be unusable for the duration of works. It is possible the work will be done in a month, but maybe longer, so the "temporary" rearrangement should be good for at least 2 months. Options:
- if weather allows, set up a a temporary outdoor "main" kitchen and set up new Snack kitchen "permanently" in current Kitchen (i.e. k20-1-2)
- more work to begin, less at end, food preparation more distributed
- set up temporary Snack kitchen in Elephant room
- less work to begin, more at end, food preparation more concentrated
Stripping down
This phase of the work is about getting rid of unwanted things and getting the room to a stage where positive construction can begin.
- ☐ remove mobile items (microwave, glasses, oats, etc)
- ☐ water off!
- ☐ remove mounted items (cupboards, shelf, radiator, sink, tap, etc)
- ☐ power off!
- ☐ remove fake-wall (left side, behind sink)
- ℹ️ unknown tasks may hide behind wall!
- ☐ remove unnecessary plumbing
- ☐ remove sewage pipe in back-right corner
- ☐ remove water pipes leading to right side
- ☐ strip walls & ceiling
- ☐ remove all tiles
- ☐ remove all wallpaper (including ceiling)
- ℹ️ needs to be done thoroughly, no pieces of paper left (likely requires spiky roller/water spray)
- ☐ remove all hooks, plugs, clips, etc.
- ☐ break out any loose plaster
- ☐ sand walls, if necessary
- celebrate 🎉
Building up
This phase of the work is about positively constructing towards the desired end state. A lot of open questions still!
- ☐ prepare walls & ceiling (i.e. smooth, flat, stable)
- ☐ plaster any holes
- ☐ if necessary plastering or complete dry-walling (hopefully not! 🙏)
- ☐ electrics
- aim: no exposed wires, good number of sockets where useful
- ☐ main light switch
- ☐ ovens/stoves ❓
- ☐ lights ❓
- ☐ parapet trunking (power strip) along both sides ❓
- ☐ plumbing
- ☐ radiator or wall heating ❓
- ☐ reroute that pipe that sticks out on the "left" side
- ☐ prepare sink inlets & outlet ❓
- preference: wall-mounted hose-tap
- ℹ️ outlet location has a degree of flexibility, wall-mounted tap not
- ☐ windowsill
- A nice bit or marble?
- ☐ ventilation❓
- ☐ Kabuff wall ❓
- if removing (See Appendix), shelves to go all the way
- ℹ️ "London" style shelf brackets have a low profile.
- ☐ dry-walling left side
- aim: to be able to have one, long stainless steel work surface without any corners, gaps or cut-outs
- from floor to head-height?
- ☐ ceiling and upper walls
- white paint that can deal with humidity ❓
- ☐ lower walls
- random saved tiles, 20 cm * 20 cm ❓
- ☐ flooring
- portal through the wall to the snack-kitchen ❓
- ... unknown unknowns 👻💀👹 ...
- Celebrate! 🎉🎉
Installation
Note that the specifics of most of these items need to be decided on before commencing the work at all
- ☐ sink
- ☐ tap
- ☐ tables
- consider differing height requirements
- ☐ overhead storage
- ☐ fridge ❓
- CelEbRat3!!! 🎉🎉🎉🎉
Appendix
Advice
Who do we know who did a comparable kitchen renovation? How much did it cost, time did it take? Advice?
- ✅ Lebenstraum Gemeinschaft Janishausen - Doug contacted
- 2026-04-21 still no response
Sewage pipe
Remove it or keep it? Removing it permanently gains a little space for the kitchen, simplifies the room shape and infrastructural complexity. Removing also requires work... Options in my order of preference
- remove pipe, relocate bathroom toilet to Kabuff
- significant work
- keep pipe, box it off (drywall)
- moderate work
- long-term missed opportunity
- remove pipe, remove bathroom toilet with no replacement
- the toilet seems useful and used!
- keep pipe, no boxing
- least work
- looks ugly, traps dirt
- (I would not be motivated to help with renovation if this option were chosen)
- remove pipe, reroute sewage through wall to staircase toilets
- most work
- this would require over 2 meters of horizontal sewage routing and a major reorganizing of pipes in upper staircase toilet
- (I would not be motivated to help with renovation if this option were chosen)
Kabuff separation wall
Remove part/all of it?
- options:
- removing the "small" side towards the entrance would allow a/the shelf to extend all the way to the door, making better use of the space
- as above, but extending all the way up: would allow a/the shelf to extend vertically to roof
- all: unclear... my imagination overflows
- any removal would brings significant costs and would only make sense to do during main action
- would require architectural considerations, possibly building in supports
- dusty breakage
- significant plastering required
- permanent damage to original and pretty door-frame
- makes it necessary to make all shelving new
- To-do: drill into wall above door frame post: if it extends to the ceiling, it's probably supporting
Heating (or not)
Options and their drawbacks
- Keep radiator (status quo)
- takes space from room
- makes windowsill less accessible
- traps dirt
- increases wall complexity for tiling, etc
- Remove radiator, no replacement
- possibly too cold in winter
- but likely fine given physical activity + heating from cooking
- possibly too cold in winter
- Remove radiator, install wall-heating panel
- work: finding parts, mounting, plumbing and plastering